Rebuild of fire-damaged Lakeview mill aiming for full-production by Feb. 2019

By Monica Lamb-Yorski
Williams Lake Tribune
August 14, 2018

Nine months after a fire destroyed Tolko’s Lakeview Division sawmill in Williams Lake the company said it hopes to resume full production by February 2019. Randy Chadney, Tolko Industries general manager BC Lumber, told the Tribune the demolition was completed in April and the rebuild is underway, noting the source of the fire could not be determined by the fire inspector, but it was confirmed it was not caused by combustible dust. “We are reconstructing the sawmill and expect to start testing some of the equipment in November,” Chadney said. Compared to the previous three-line sawmill at Lakeview, the new one will be a two-line sawmill with a canter line and a head rig.